Goddard School of Franconia: Oldcastle Storefront in a Former Laser Tag Arena
The Goddard School of Kingstowne (Franconia/Springfield) turned a 20,000 square foot former laser tag arena in Fairfax County, Virginia into a preschool, glazed with Oldcastle BuildingEnvelope FG-3000T storefront and WS-500 wide stile entrances in clear anodized. MP Drafting drew the shop drawings for Specialty Glass, Inc.
The Goddard School of Kingstowne (Franconia/Springfield) is a preschool at 5508 Franconia Road in Franconia, Virginia, in Fairfax County just outside Alexandria. It occupies a 20,000 square foot pre-engineered metal building on 1.8 acres that opened as a roller skating rink and spent its last nineteen years as ShadowLand Laser Adventures, a laser tag and arcade venue. Architecture Inc. of Reston designed the exterior for the whole building and the interiors for the childcare portion. The franchisees bought the property in February 2025 with a first quarter 2026 opening in mind, and the school is open and enrolling.
MP Drafting drew the shop drawings for Specialty Glass, Inc., the glazing contractor, out of Martinsburg, West Virginia. The package is Oldcastle BuildingEnvelope storefront and entrances, FG-3000T framing with WS-500 wide stile doors, all clear anodized, with Sika Aluminum Gray as the exterior sealant. Matt and Jacob drafted the set, thirteen sheets over two submittals in April and May 2025. The part of this job worth some time is what the storefront went into, because a laser tag arena is a building designed to keep daylight out, and this set put daylight back in.
The Oldcastle Storefront Package
- Oldcastle BuildingEnvelope FG-3000T storefront framing, 2 inch by 4-1/2 inch, 1 inch insulating glass, clear anodized
- Oldcastle BuildingEnvelope WS-500 wide stile entrance doors, clear anodized, with the hardware sets called out on the door elevations
- Glass GL-1T: 1 inch insulated unit, 1/4 inch clear tempered, 1/2 inch argon space, 1/4 inch clear tempered, SN68 low-e on the #2 surface. GL-1S: the same unit with a warm gray spandrel coating, at the head band of the classroom openings
- Exterior sealant: Sika Aluminum Gray
- Shop drawings: MP Drafting & Design, 13 sheets, two submittals (April 28 and May 28, 2025). Drafters: Matt, Jacob
- Glazing contractor: Specialty Glass, Inc.
- Architect: Architecture Inc.
The FG-3000T is the thermal version of OBE’s 2 inch by 4-1/2 inch flush glaze storefront, which is the depth most storefront in this part of the country gets drawn at, and it takes 1 inch insulating glass. Fairfax County is IECC climate zone 4A, so a thermally broken frame is the normal answer on a building that is conditioned all day with this much new glass in it. Most of the set is one elevation repeated: Elevation B, the classroom window, is 15 feet wide by 8 feet 3 inches tall, five lites across with a spandrel row along the top, and there are ten of them. Elevation A is the entrance, 18 feet 4 inches wide and 12 feet 11 inches tall, with a single 3 foot by 8 foot WS-500 leaf and a transom over it. The WS-500 is OBE’s wide stile door, the heaviest of its three standard stiles, and on this job it hangs in the FG-3000T framing. If you need thermal breaks explained, the Glazing Systems 101 course on LearnGlazing covers it, and the set does not. Everything else in the set is OBE’s system details for head, jamb, and sill, the same way every storefront set out of this office does, with the frame sizes and door elevations on the sheets the installer and the fabricator both work from.
Windows Where There Were None
Architecture Inc. describes the building it started with as “a dark, windowless entertainment venue,” and that is the whole drafting story in one line. Their project page says the reuse brought in new glazing, new finishes, and a reworked plan to get daylight into 15,000 square feet of childcare space, with a 7,000 square foot playground outside and a SafeSplash Swim School in the remaining quarter of the building. One of the owners told FFXnow in February 2025, “The building is going to stay as is, but we will be doing some major improvements.” For the storefront, that sentence means every opening in the set is a new opening cut into an existing wall, and nobody had a window there before.
That changes where the numbers come from. On a new building the drafter works from the architect’s wall section and the framer builds the opening to it, so the plan dimension and the field dimension are usually the same number. On a reuse the framer cuts the opening in a wall that was never meant to have one, so every rough opening in this set is taken from the architect’s A2.02 elevations and marked V.I.F., with the frame size drawn 1 inch under it for a 1/2 inch joint each side. General note 4 on the cover sheet says the rest: all dimensions field verified before glass ordering and fabrication. You can see what the framer was building in the jamb details, metal stud with sheathing and EIFS above the sill line and brick over CMU at the knee wall, and at the CMU jamb the set carries a contractor note to confirm the fastener location because a strap anchor is required at that condition. The sill flashing is the one piece of the perimeter the set assigns to the glazier, .04 inch flashing by Specialty Glass, and everything else around the frame is by others.
A Wide Stile at a Preschool Door
The entrance doors are wide stile, and a wide stile is a tradeoff a PM should make on purpose. It is more aluminum, more weight on the closer and the pivots, and less glass in the same opening than a medium stile would give. What it buys is a door that takes a closer cycling from 7:00 am to 6:00 pm five days a week, with strollers, car seats, and a parent’s hip pushing it open, and a stile wide enough to carry a full size exit device and a lock without the hardware crowding the glass. The hardware sets on the elevations read like a preschool door should: continuous hinge, rim exit device, parallel arm closer, sweep, threshold, and an inner finger guard that closes the hinge side gap so a small hand cannot get into it. The three classroom and staff doors get delayed egress exit devices on top of that. On a school door with that much traffic, the wide stile is the trade most of us would make too, and the door elevations carry the hardware sets so the doors get prepped once.
Roller Rink, Laser Tag, Pre-K
The building has had three lives, and the owners tell the first two themselves. It opened as a roller skating rink, and from 2006 until 2025 it was ShadowLand, which Patch once described with eleven party rooms, an arcade, and a karaoke studio under one roof. The property changed hands in early 2025, as Virginia Business reported, and the new owners already ran a Goddard School in Alexandria West that was full with a wait list. The Franconia school is built to hold nearly 180 children in classrooms sorted by age, from infants to pre-K, with a lobby bookcase the architect built as the first thing a family sees. Whether a third school follows is not something anyone has announced.
What the Framer Builds Is the Dimension
When storefront goes into an opening cut in an existing building, every R.O. on the set is a target with V.I.F. next to it, and the cover sheet note says the dimensions get field verified before glass ordering and fabrication. Have the installer measure each opening after the framer has built it and send the numbers back before the frames are cut. If a measured opening comes in different from the sheet, the frame size changes and the 1/2 inch joint stays, so the first time the aluminum meets the wall is not install day.
Storefront Shop Drawings for Glazing Contractors
MP Drafting draws storefront, curtain wall, and entrance shop drawings for glazing contractors across the country, on manufacturer systems from OBE, Tubelite, YKK, Kawneer, and the rest. The set goes out ready for the fabricator and the installer to work from the same sheets. MP has drawn other Oldcastle packages, including the Motown Museum expansion. If your next job is putting windows into a building that was built not to have any, send us the plans and the framer’s numbers.
Use Education to Get Ahead
Every missed deadline creates a ripple effect. Delayed fabrication, wrong orders, wasted time in the field. One way to cut that risk is by training your team to review drawings effectively.
LearnGlazing’s Shop Drawing Course makes it easier to spot issues before they become emergencies. Explore the course.